Project work packages are typically decomposed into smaller components called activities t

时间:2021-05-05 02:04:25 解答: 86 次

Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.

A.reviewing

B.estimating

C.auditing

D.expecting

正确答案:

B解析:把项目工作包分解成更小的结构称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。