Estimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,and resource calendars.
A.milestone
B.baseline
C.quality
D.work
Estimating activity durations uses information on activity scope of(74),required resource types,estimated resource quantities,and resource calendars.
A.milestone
B.baseline
C.quality
D.work
D解析:估算活动历时使用的信息包括:活动的工作范围、所需资源类型、估算的资源数量以及资源日历。