(c) Using information from the case, assess THREE risks to the Giant Dam Project. (9 marks)
(c) Using information from the case, assess THREE risks to the Giant Dam Project. (9 marks)
(c) Assessment of three risksDisruption and resistance by Stop-the-dam. Stop-the-dam seems very determined to delay and disrupt progress as much aspossible. The impact of its activity can be seen on two levels. It is likely that the tunnelling and other ‘