Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).
A.Risk avoidance
B.Risk acceptance
C.Risk mitigation
D.Contingency plan
Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).
A.Risk avoidance
B.Risk acceptance
C.Risk mitigation
D.Contingency plan
C