Developing the project schedule is often an iterative process. It determines the planned s

时间:2021-05-05 02:04:17 解答: 90 次

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend

正确答案:

B解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。